The following are REQUIRED INSPECTIONS PURSUANT TO N.J.A.C. 5:23-2.18

NEW BUILDINGS-ADDITIONS-RENOVATIONS-ALTERATIONS (other

Inspections may be required depending on the scope of the project.  Consult the Subcode

Officials if you have any questions.):

1.     Footing inspections-Bottom of trench-PRIOR to the pouring of concrete.

2.     Wall forms & Steel-PRIOR to the pouring of concrete.

3.     Foundation Inspection-PRIOR to the placement of backfill.

4.     Sheathing inspection-PRIOR to siding & roofing

5.     Slab inspection-PRIOR to the placement of concrete.

6.     Plumbing rough installation and air test for gas piping.

7.     Electric rough wiring.

8.     All trenches for plumbing and electric.

9.     Framing inspection-AFTER passing Electrical, Plumbing and BEFORE insulation.  ALL  FIRE BLOCKING AND PENETRATIONS MUST BE DONE AT FRAMING INSPECTION

10.     Insulation inspection-PRIOR to the installation of gypsum board.

11.   Final Electric, Plumbing & Fire.  Building after all others have passed.

For all inspection requests call the Technical Assistants @ 732-356-0833 ext. 630.  You must have the following information In order to request an inspection.  (PERMIT #, BLOCK/LOT, NAME & ADDRESS AND TYPE OF INSPECTION.)  Provide any other information that may be needed. ONLY CALL FOR INSPECTIONS WHEN THE WORK IS READY.

 If you have any questions regarding these procedures please call Michael Wright, Construction